File #: 15-0814    Name: New Juvenile Hall Quarterly Report
Type: General Agenda Item Status: Agenda Ready
File created: 7/14/2015 In control: Budget Committee
On agenda: 7/29/2015 Final action:
Title: Receive Quarterly Budget and Schedule Status Report on the New Juvenile Hall, Project 8811 (Project), for the period ending June 30, 2015.
Sponsors: Public Works / RMA
Attachments: 1. Project Milestone Schedule, 2. Project Budget
Title
Receive Quarterly Budget and Schedule Status Report on the New Juvenile Hall, Project 8811 (Project), for the period ending June 30, 2015.
Report
RECOMMENDATION:
It is recommended that the Budget Committee receive a Quarterly Budget and Schedule Status Report on the New Juvenile Hall, Project 8811 (Project), for the period ending June 30, 2015.

SUMMARY/DISCUSSION:
Key schedule components and budget status are summarized below.

Budget and Schedule: The Project is on budget. On April 1, 2015, Preliminary Plan (Design Development) documents were submitted to the Board of State and Community Corrections (BSCC) for review. Approval by the State Public Works Board (SPWB) is anticipated in July 2015. Construction will start in May 2016.

State Milestones: The next submittal to SPWB is for Approval of Construction Documents and to issue for bidding in January 2016.

Design: Architect DLR Group is on schedule, with 100 percent of the Preliminary Plan Phase complete. Overall, Design is 75 percent complete. Bid documents will be taken to the Board of Supervisors for approval on November 17, 2015.

CEQA Process: The Board of Supervisors adopted the Mitigated Negative Declaration for the Project on May 19, 2015; the Notice of Determination was filed with the Recorder - County Clerk on May 20, 2015. The 30 day challenge period concluded on June 19, 2015, no challenge was filed.

Real Estate Due Diligence: The County's Real Estate Due Diligence submittal to the Department of General Services was approved.

OTHER AGENCY INVOLVEMENT:
Resource Management Agency - Public Works and Probation continue to work jointly with BSCC to meet all State requirements to maintain the conditional award by moving the project forward in design.

FINANCING:
Total estimated Project cost is $52,791,824, of which $17,791,824 was approved by the Board of Supervisors as the County's match. To-date expenditures total $2,079,692, including Fiscal Year 2014-15 expe...

Click here for full text