File #: A 15-299    Name: Telfer Oil Contract for Sealcoat FY 16
Type: BoS Agreement Status: Passed
File created: 8/12/2015 In control: Board of Supervisors
On agenda: 9/1/2015 Final action: 9/1/2015
Title: a. Award a contract to Telfer Oil Company, the lowest responsible bidder, for the Procurement (Delivery and Application) of Asphalt Emulsion for the Seal Coat FY16, Project No. 5516, in the total amount of $280,262.27; b. Approve the Performance and Payment Bonds executed and provided by Telfer Oil Company; c. Authorize a contingency (not to exceed 10% of the contract amount) to provide funding for approved contract change orders; d. Authorize the Director of Public Works to execute the contract and subject to the terms of the Public Contract Code approve change orders to the contract that do not exceed 10% of the original contract amount and do not significantly change the scope of work; and e. Authorize the Director of Public Works to execute a Certificate of Completion and record a Notice of Completion with the County Recorder when he determines that the contract is complete in all respects in accordance with Plans and Special Provisions for the construction of Procurement (Deli...
Sponsors: Public Works / RMA
Attachments: 1. Board Report, 2. Contract for Telfer Oil Co, 3. Bonds, 4. Project Budget, 5. Bid Summary, 6. Location Map, 7. Completed Board Order, 8. Fully Executed Agreement betweeen the County of Monterey and Telfer Oil Company, 9. Fully Executed Agreement between the County of Monterey and Telfer Oil Company
Title
a. Award a contract to Telfer Oil Company, the lowest responsible bidder, for the Procurement (Delivery and Application) of Asphalt Emulsion for the Seal Coat FY16, Project No. 5516, in the total amount of $280,262.27;
b. Approve the Performance and Payment Bonds executed and provided by Telfer Oil Company;
c. Authorize a contingency (not to exceed 10% of the contract amount) to provide funding for approved contract change orders;
d. Authorize the Director of Public Works to execute the contract and subject to the terms of the Public Contract Code approve change orders to the contract that do not exceed 10% of the original contract amount and do not significantly change the scope of work; and
e. Authorize the Director of Public Works to execute a Certificate of Completion and record a Notice of Completion with the County Recorder when he determines that the contract is complete in all respects in accordance with Plans and Special Provisions for the construction of Procurement (Delivery and Application) of Asphalt Emulsion for the Seal Coat FY16, Project No. 5516, performed by Telfer Oil Company.
Report
RECOMMENDATION:
It is recommended that the Board of Supervisors:

a. Award a contract to Telfer Oil Company, the lowest responsible bidder, for the Procurement (Delivery and Application) of Asphalt Emulsion for the Seal Coat FY16, Project No. 5516, in the total amount of $280,262.27;

b. Approve the Performance and Payment Bonds executed and provided by Telfer Oil Company;

c. Authorize a contingency (not to exceed 10% of the contract amount) to provide funding for approved contract change orders;

d. Authorize the Director of Public Works to execute the contract and subject to the terms of the Public Contract Code approve change orders to the contract that do not exceed 10% of the original contract amount and do not significantly change the scope of work; and

e. Authorize the Director of Public Works to execute a Certificate of ...