File #: 16-163    Name: East/West Wing Renovation CIC Quarterly Report - 2-8-16
Type: General Agenda Item Status: Agenda Ready
File created: 2/2/2016 In control: Capital Improvement Committee
On agenda: 2/8/2016 Final action:
Title: Receive a Quarterly Status Report on the East/West Wing Renovation, Project 8862 (Project), for the period ending December 31, 2015.
Attachments: 1. Attachment - East West Wing Renovation Project Milestone Schedule - 2-8-16

Title

Receive a Quarterly Status Report on the East/West Wing Renovation, Project 8862 (Project), for the period ending December 31, 2015.

Report

RECOMMENDATION:

It is recommended that the Capital Improvement Committee (CIC) receive a Quarterly Status Report on the East/West Wing Renovation, Project 8862 (Project), for the period ending December 31, 2015.

 

SUMMARY/DISCUSSION:

Budget and Schedule:  The Project is on budget and schedule.  In September 2015, Certificates of Participation (COP) became available to fund the Project.

 

Design:  Schematic Design was completed in November 2015 and the Design Development Phase was started.  A Selective Demolition Package was prepared and permitted.  A Window & Door Replacement Package has been prepared and is being costed.

 

Construction:  A Job Order Contract was prepared and negotiated with Pueblo Construction for doing selective demolition.   Construction fencing was erected and utilities to the site were disconnected and capped. 

 

OTHER AGENCY INVOLVEMENT:

Resource Management Agency-Public Works continues to work closely with the County Administrative Office and the District Attorney’s Office on the development of the Project.

 

FINANCING:

The Project is currently expected to be on schedule and budget.  The Project is financed through a combination of COP proceeds and County funds.

 

 

Prepared by:  Judy Jeska, Project Manager III (831) 755-8964

 

Approved by:  Dewayne Woods, Assistant County Administrative Officer

 

Attachment:  Project Milestone Schedule