File #: BC 16-028    Name: East/West Wing Renovation Project Quarterly Update - Aug 2016
Type: Budget Committee Status: Agenda Ready
File created: 7/18/2016 In control: Budget Committee
On agenda: 8/31/2016 Final action:
Title: Receive a Quarterly Budget and Schedule Status Report on the East-West Wing Renovation, Project 8864 (Project), for period ending June 30, 2016.
Attachments: 1. East West Renovation Project Budget to 6-30-16, 2. East West Renovation Project Milestones - Aug 2016

Title

Receive a Quarterly Budget and Schedule Status Report on the East-West Wing Renovation, Project 8864 (Project), for period ending June 30, 2016.

Report

RECOMMENDATION:

It is recommended that the Budget Committee receive a Quarterly Budget and Schedule Status Report on the East-West Wing Renovation, Project 8864 (Project), for period ending June 30, 2016.

 

SUMMARY/DISCUSSION:

Key schedule components and budget status are summarized below.

 

Budget and Schedule:  The overall Project is on budget and schedule.

 

Design:  Wald Ruhnke Dost, Architects, finalized the 95% Construction Document Plan Phase and submitted for Code and Plan Check review over the summer months.

 

Milestones:  The next milestone will be Board of Supervisors approval to advertise for bid in November, 2016.

 

Selective Demolition:  Selective abatement and demolition of the interior was completed.  Fencing was retained for the window/door replacement phase.

 

Window and Door Replacement:   Contract was finalized by the General Contractor for their subcontract.  The first review of the shop drawings was completed and returned to the subcontractor for updates. 

 

CEQA and SEIR Process:  The CEQA and SEIR process is complete.

 

OTHER AGENCY INVOLVEMENT:

RMA-Public Works coordinated with the County Administrative Office and all selected agency tenants who will reside in the East-West Wing Building to develop the Project Plans and Specifications. 

 

FINANCING:

The project is financed by County funds in the amount of $624,623 and Certificates of Participation (COPs) in the amount of $36 million issued for the specific purpose of completing the East-West Wing renovation project. Total expenditures through the end of this quarter are $6,520,966.  Funding for this project is contained in Fund 404 - Facilities Master Plan Projects.

 

 

Prepared by: Judy Jeska, Project Manager III

 

Approved by: Dewayne Woods, Assistant County Administrative Officer

 

Attachments:                     Project Milestone Schedule; Project Budget