a. Support Natividad Medical Center to increase the total project cost approved by the Board of Supervisors for $1,156,036 for The Medical Office Buildout - Floor One by $1,059,716 to a revised total project cost of $2,215,752.; and
b. Support Natividad Medical Center to increase the total project cost approved by the Board of Supervisors for $800,000 for The Building 400 - Mechanical Upgrade by $44,381 to a revised total project cost of $844,381; and
c. Support Award of an agreement in the total amount of $2,604,675 for the construction component to Tombleson Inc. the lowest responsible and responsive base bidder, for Natividad Medical Center for the above mentioned projects; and
d. Support to approve the Performance and Payment Bonds executed and provided by Tombleson Inc.; and
e. Support to authorize a contingency (not to exceed 10% of the contract amount) to provide funding for approved contract change order.
Report
RECOMMENDATION:
It is recommended that the Capital Improvement Committee:
a. Support Natividad Medical Center to increase the total project cost approved by the Board of Supervisors for $1,156,036 for The Medical Office Buildout -Floor One by $1,059,716 to a revised total project cost of $2,215,752.; and
b. Support Natividad Medical Center to increase the total project cost approved by the Board of Supervisors for $800,000 for The Building 400 - Mechanical Upgrade by $44,381 to a revised total project cost of $844,381; and
c. Support Award of an agreement in the total amount of $2,604,675 for the construction component to Tombleson Inc. the lowest responsible and responsive base bidder, for Natividad Medical Center for the above mentioned projects; and
d. Support to approve the Performance and Payment Bonds executed and provided by Tombleson Inc.; and
e. Support to authorize a contingency (not to exceed 10% of the contract amount) to provide funding for approved contract change order.