File #: BC 16-041    Name: Support to Award Building 400 1st floor and HVAC
Type: Budget Committee Status: Agenda Ready
File created: 9/16/2016 In control: Budget Committee
On agenda: 9/28/2016 Final action:
Title: a. Support Natividad Medical Center to increase the total project cost approved by the Board of Supervisors for $1,156,036 for MOB Buildout - Floor One by $1,059,716 to a revised total project cost of $2,215,752.; and b. Support Natividad Medical Center to increase the total project cost approved by the Board of Supervisors for $800,000 for The Building 400 - Mechanical Upgrade by $44,381 to a revised total project cost of $844,381; and c. Support Award of an agreement in the total amount of $2,604,675 for the construction component to Tombleson Inc. the lowest responsible and responsive base bidder, for Natividad Medical Center for the above mentioned projects; and d. Support to approve the Performance and Payment Bonds executed and provided by Tombleson Inc.; and e. Support to authorize a contingency (not to exceed 10% of the contract amount) to provide funding for approved contract change order.
Attachments: 1. Exhibit 2 - Project Schedule.pdf, 2. Exhibit 1 - Project Budget.pdf
Title
a. Support Natividad Medical Center to increase the total project cost approved by the Board of Supervisors for $1,156,036 for MOB Buildout - Floor One by $1,059,716 to a revised total project cost of $2,215,752.; and
b. Support Natividad Medical Center to increase the total project cost approved by the Board of Supervisors for $800,000 for The Building 400 - Mechanical Upgrade by $44,381 to a revised total project cost of $844,381; and
c. Support Award of an agreement in the total amount of $2,604,675 for the construction component to Tombleson Inc. the lowest responsible and responsive base bidder, for Natividad Medical Center for the above mentioned projects; and
d. Support to approve the Performance and Payment Bonds executed and provided by Tombleson Inc.; and
e. Support to authorize a contingency (not to exceed 10% of the contract amount) to provide funding for approved contract change order.

Report
RECOMMENDATION:
It is recommended that the Budget Committee:

a. Support Natividad Medical Center to increase the total project cost approved by the Board of Supervisors for $1,156,036 for The Medical Office Buildout -Floor One by $1,059,716 to a revised total project cost of $2,215,752.; and
b. Support Natividad Medical Center to increase the total project cost approved by the Board of Supervisors for $800,000 for The Building 400 - Mechanical Upgrade by $44,381 to a revised total project cost of $844,381; and
c. Support Award of an agreement in the total amount of $2,604,675 for the construction component to Tombleson Inc. the lowest responsible and responsive base bidder, for Natividad Medical Center for the above mentioned projects; and
d. Support to approve the Performance and Payment Bonds executed and provided by Tombleson Inc.; and
e. Support to authorize a contingency (not to exceed 10% of the contract amount) to provide funding for approved contract change order.

SUMMARY/DISCUSSION:
NMC desires to perform a tenant improvement to th...

Click here for full text