File #: 17-0198    Name: East/West Wing Quarterly Budget & Schedule Project Report - Mar 2017
Type: General Agenda Item Status: Agenda Ready
File created: 2/27/2017 In control: Capital Improvement Committee
On agenda: 4/10/2017 Final action:
Title: Receive a Quarterly Budget and Schedule Status Report on the East-West Wing Renovation, Project 8864 (Project), for period ending December 31, 2016.
Attachments: 1. Staff Report, 2. East-West Budget Milestone Schedule - Mar 2017, 3. East-West Wing Budget - Mar 2017

Title

Receive a Quarterly Budget and Schedule Status Report on the East-West Wing Renovation, Project 8864 (Project), for period ending December 31, 2016.

Report

RECOMMENDATION:

It is recommended that the Capital Improvement Committee receive a Quarterly Budget and Schedule Status Report on the East-West Wing Renovation, Project 8864 (Project), for period ending December 31, 2016.

 

SUMMARY/DISCUSSION:

Key schedule components and budget status are summarized below.

 

Budget and Schedule:  The overall Project is on budget and schedule.

 

Design:  Wald Ruhnke Dost, Architects; design is complete.

 

Milestones:  The next milestones include; Bid opening February 2, 2017; Board of Supervisors award of construction contract March 21, 2017; start of construction May, 2017.

 

Selective Demolition:  Selective abatement and building interior and courtyard landscaping demolition is complete.  Fencing to the courtyard was retained for the tenant improvement phase.

 

Window and Door Replacement:   Window replacement is complete.

 

CEQA and SEIR:  The CEQA and SEIR process is complete.

 

Project Bidding:  The Board of Supervisors authorized advertising for construction bids on December 13, 2016.  The first addendum to the construction documents was released on December 28, 2016. 

 

OTHER AGENCY INVOLVEMENT:

RMA-Public Works coordinated with the County Administrative Office and all selected agency tenants who will reside in the East-West Wing Building to develop the Project Plans and Specifications. 

 

FINANCING:

The project is financed by Certificates of Participation (COPs) in the amount of $52,000,000 issued for the specific purpose of completing both the Schilling Place and East/West Wing renovation projects.  Specifically, the East/West Renovation Project is funded by a COP allocation of $36,000,000 and County funds in the amount of $624,623 for a pre-bid total project cost of $36,624,623.  Total expenditures through the end of this quarter are $7,748,799.  Funding for this project is contained in Fund 404 - Facilities Master Plan Projects.

 

Prepared by: Judy Jeska, Project Manager III

 

Approved by: Dewayne Woods, Assistant County Administrative Officer

 

 

 

Dated:  February 24, 2017

 

Attachments:                     Project Milestone Schedule; Project Budget