File #: BC 17-028    Name: Schilling Place Quarterly Budget & Project Schedule Report - Mar 2017
Type: Budget Committee Status: Agenda Ready
File created: 2/27/2017 In control: Budget Committee
On agenda: 3/29/2017 Final action:
Title: Receive a Quarterly Budget and Schedule Status Report on Schilling Place Tenant Improvement, Project 8862 (Project), for the period ending December 31, 2016.
Attachments: 1. Schilling Milestone Schedule - Mar 2017, 2. Schilling Pl Budget - Mar 2017
Title
Receive a Quarterly Budget and Schedule Status Report on Schilling Place Tenant Improvement, Project 8862 (Project), for the period ending December 31, 2016.
Report
RECOMMENDATION:
It is recommended that the Budget Committee receive a Quarterly Budget and Schedule Status Report on Schilling Place Tenant Improvement, Project 8862 (Project), for the period ending December 31, 2016.

SUMMARY/DISCUSSION:
Key schedule components and budget status are summarized below.

Budget and Schedule: The overall Project is on budget and schedule.

Design: Design is complete.

Construction Contract Award: Contract award to Ausonio Incorporated is complete

Milestones: The next milestones include: Construction completion February 21, 2017, start of tenant move-ins April 3, 2017, completion of tenant move-ins June 30, 2017.

Construction: Above ceiling electrical/ data work, tiling in restrooms/gym, storefront framing, carpeting, painting, casework shop drawings, coordination of moving existing furniture, site demolition/grading, and door hardware clarifications in process. Staff anticipates construction schedule will slip but at this time no time extension claim has been submitted by the contractor.

Roof: Warranty work on water intrusions continues as discovered.

Move Coordination: Support to tenants as they prepare for their moves continues. Seating matrix listing computer and phone numbers coordinated with a seating floor plan and cubicle/room number signage completed. Adjustments made to move schedule to accommodate tenant requirements and possible construction delay.

CEQA : Project is Categorically Exempt.

OTHER AGENCY INVOLVEMENT:
RMA-Public Works coordinated with the County Administrative Office and all selected agency tenants who will reside at Schilling Place to develop the Project Plans and Specifications.

FINANCING:
The project is financed by Certificates of Participation (COPs) in the amount of $52,000,000 issued for the specific purpose of ...