File #: BC 17-116    Name: Quarterly Report for the East/West Wing - BC
Type: Budget Committee Status: Agenda Ready
File created: 8/14/2017 In control: Budget Committee
On agenda: 8/30/2017 Final action:
Title: Receive a Quarterly Budget and Schedule Status Report on the East-West Wing Renovation, Project 8864 (Project), for period ending June 30, 2017.
Attachments: 1. BC Report, 2. 8-16-17 Attachment - East West Wing-Milestone Schedule, 3. 8-16-17 Attachment - East West Wing - Budget

Title

Receive a Quarterly Budget and Schedule Status Report on the East-West Wing Renovation, Project 8864 (Project), for period ending June 30, 2017.

Report

RECOMMENDATION:

It is recommended that the Budget Committee receive a Quarterly Budget and Schedule Status Report on the East-West Wing Renovation, Project 8864 (Project), for period ending June 30, 2017.

 

SUMMARY/DISCUSSION:

Key schedule components and budget status are summarized below.

 

Budget and Schedule:  The overall Project is on budget and schedule.

 

Selective Demolition - Phase I:  Interior removal of building systems and partitions is complete.

 

Window and Door Replacement - Phase I:   Installation of eighty percent of the windows was completed.  The remaining windows and doors are part of the Phase II, Tenant Improvements Project. 

 

Design - Phase II Tenant Improvement:  Drawings for Phase II Tenant Improvement Project and all permitting requirements are complete.

 

CEQA and SEIR:  The CEQA and SEIR process is complete.  Mitigation Monitoring Program Reporting is underway.

 

Milestones:  November will mark the midway point of the construction process.

 

Construction:  Avila Construction received the contract award and construction began May 2017.  Site fencing was erected and encroachment permits included the re-routing of traffic along Alisal and Church Streets.  With the site secure the following began:  demolition and abatement of the roofing materials; mechanical equipment ordered; interior walls x-rayed for existing steel placement; remaining courtyard vegetation removed; grading and base rock installed; demolition of interior concrete wall openings; layout of new walls; elevator submittal package reviewed and adjustments made; steel shop fabrications started, and the review of all technical submittal packages.  

 

OTHER AGENCY INVOLVEMENT:

RMA-Public Works coordinated with the County Administrative Office and all selected agency tenants who will reside in the East-West Wing Building to develop the Project Plans and Specifications. 

 

FINANCING:

The project is financed by Certificates of Participation (COPs) in the amount of $52,000,000 issued for the specific purpose of completing both the Schilling Place and East/West Wing renovation projects.  Specifically, the East/West Renovation Project is funded by a COP allocation of $36,000,000 and County funds in the amount of $2,930,844 for a total project cost of $38,930,844.  Total expenditures through the end of this quarter are $10,480,256.  Funding for this project is contained in Fund 404 - Facilities Master Plan Projects.

 

Prepared by: Judy Jeska, Project Manager III

 

Approved by: Dewayne Woods, Assistant County Administrative Officer

 

Attachments:                     Project Milestone Schedule; Project Budget