File #: BC 18-015    Name: Raftelis Amendment No. 1
Type: Budget Committee Status: Agenda Ready
File created: 1/22/2018 In control: Budget Committee
On agenda: 1/31/2018 Final action:
Title: Support adopting the resolution: a. Approving Amendment No. 1 to the Professional Services Agreement with Raftelis Financial Consultants Inc. for an extension of time to June 30, 2018; and b. Authorizing the General Manager to execute the Amendment.
Attachments: 1. Board Report, 2. Amendment No.pdf, 3. Agreement for Services, 4. Resolution
Title
Support adopting the resolution:
a. Approving Amendment No. 1 to the Professional Services Agreement with Raftelis Financial Consultants Inc. for an extension of time to June 30, 2018; and
b. Authorizing the General Manager to execute the Amendment.
Report
RECOMMENDATION:
It is recommended that the Budget Committee:

Support adopting the resolution:
a. Approving Amendment No. 1 to the Professional Services Agreement with Raftelis Financial Consultants Inc. for an extension of time to June 30, 2018; and
b. Authorizing the General Manager to execute the Amendment.

SUMMARY/DISCUSSION:
Raftelis Financial Consultants Inc. (RFC) was hired by the Monterey County Water Resource Agency for the primary objectives of reviewing the Agency Benefit Assessments in Zones 2B, 2Y, and 2Z; the Water Delivery and Service charges; ongoing Project Management; and, to provide an updated assessment methodology/analysis and a cost of service approach. Upon completion of the cost of service analysis, a comparison of the three methodologies would be presented and appended to the updated model. The three methodologies consisted of:

1. Existing assessment methodology
2. Revised assessment methodology developed
3. Cost of Service methodology developed

A model of the above methodologies was presented to the Board on March 20, 2017 and it was recommended that RFC meet with the 22 landowners in Zone 2B to discuss the options presented to them. One of the popular options was to merge the Water Delivery charge in Fund 131 of $5.83 and Water Service charge in Fund 134 of $67.82 before requesting an increase on assessments.

On August 25, 2017, RFC met with the Zone 2B landowners at the Water Quality and Operations meeting at Monterey One Water and the land owners agreed to the RFC option to update ordinance 3789 and clarifying Resolution 00-172 to merge the service and delivery charges into one utility charge to accomplish the following:

* By combining the ...

Click here for full text