Title: PLN170076 - HIRSCHFIELD Public hearing to consider a partial demolition and rebuild of an existing 3,126 square foot single family dwelling to include demolition of approximately 350 square feet and an addition of approximately 3,300 square feet. Project Location: 1268 Cantera Court, Pebble Beach, Del Monte Forest Land Use Plan. CEQA Action: Categorically Exempt per CEQA Sections 15303 (a) and 15304
Attachments: 1. Staff Report, 2. Exhibit A - Project Data Sheet, 3. Exhibit B - Draft Resolution, 4. Exhibit C - Vicinity Map, 5. RESza_18-011_PLN170076_030818
Title
PLN170076 - HIRSCHFIELD
Public hearing to consider a partial demolition and rebuild of an existing 3,126 square foot single family dwelling to include demolition of approximately 350 square feet and an addition of approximately 3,300 square feet.
Project Location: 1268 Cantera Court, Pebble Beach, Del Monte Forest Land Use Plan.
CEQA Action: Categorically Exempt per CEQA Sections 15303 (a) and 15304
Report
RECOMMENDATION:
It is recommended that the Zoning Administrator adopt a resolution to:
a. Find that the project is a remodel and addition to an existing single family residence in a residential zone which qualifies as a Class 3 Categorical Exemption per Section 15303 (a) of the CEQA Guidelines; and tree removal which do not involve in the removal of healthy, mature, or scenic trees, which qualifies as a Class 4 Categorical Exemption per Section 15304. and does not meet any exceptions under Section 15300.2;
b. Approve a Combined Development Permit consisting of:
1) A Coastal Administrative Permit and Design Approval for a partial demolition and rebuild of an existing 3,126 square foot single family dwelling, to include the demolition of approximately 350 square feet, and an addition of approximately 3,300 square feet; and
2) A Coastal Development Permit for the removal of two Monterey Pine trees (14" and 16" in diameter)
The attached draft resolution includes findings and evidence for consideration (Exhibit B).
Staff recommends approval subject to 16 conditions of approval.

PROJECT INFORMATION:
Agent: John Moore Design
Property Owner: Scott E and Molly Hirschfield
APN: 008-234-011-000
Parcel Size: 1.28 acres
Zoning: "LDR/1.5-D (CZ)" Low Density Residential/1.5 units per acre-Design Control in the Coastal Zone
Plan Area: Del Monte Forest Land Use Plan
Flagged and Staked: Yes

SUMMARY/DISCUSSION:
Setting:
The project site is located in the southwest corner of Cantera Court, in the Del Monte Forest of Pebble Beach. The building envelope is loca...