File #: 18-491    Name: New Juvenile Hall Project No. 8811-Change Order 18 and Change Order 19
Type: General Agenda Item Status: Consent Agenda
File created: 4/27/2018 In control: Board of Supervisors
On agenda: 5/8/2018 Final action:
Title: a. Approve issuance of Change Order 18 for plumbing material changes to Zovich Construction, Inc. on the New Juvenile Hall Project, Project No. 8811, Bid Package No. 10590 in the amount of $590,000 and authorizing the execution by the County; b. Approve issuance of Change Order 19 for additional foundation work to Zovich Construction, Inc. on the New Juvenile Hall Project, Project No. 8811, Bid Package No. 10590 in the amount of $935,000 and authorizing the execution by the County; and c. Authorize the Director of the Resource Management Agency to execute Change Orders 18 and 19 to Zovich Construction, Inc. for the New Juvenile Hall Project, Project No. 8811, Bid Package 10590.
Sponsors: Public Works / RMA
Attachments: 1. Board Report, 2. Attachment A - Change Order 18, 3. Attachment B - Change Order 19, 4. Completed Board Order
Date Action ByActionResultAction DetailsSearchable Meeting DetailsVideo
No records to display.
Title
a. Approve issuance of Change Order 18 for plumbing material changes to Zovich Construction, Inc. on the New Juvenile Hall Project, Project No. 8811, Bid Package No. 10590 in the amount of $590,000 and authorizing the execution by the County;
b. Approve issuance of Change Order 19 for additional foundation work to Zovich Construction, Inc. on the New Juvenile Hall Project, Project No. 8811, Bid Package No. 10590 in the amount of $935,000 and authorizing the execution by the County; and
c. Authorize the Director of the Resource Management Agency to execute Change Orders 18 and 19 to Zovich Construction, Inc. for the New Juvenile Hall Project, Project No. 8811, Bid Package 10590.
Report
RECOMMENDATION:
It is recommended that the Board of Supervisors:
a. Approve issuance of Change Order 18 for plumbing material changes to Zovich Construction,
Inc. on the New Juvenile Hall Project, Project No. 8811, Bid Package No. 10590 in the
amount of $590,000 and authorizing the execution by the County.
b. Approve issuance of Change Order 19 for additional foundation work to Zovich Construction,
Inc. on the New Juvenile Hall Project, Project No. 8811, Bid Package No. 10590 in the
amount of $935,000 and authorizing the execution by the County.
c. Authorize the Director of the Resource Management Agency to execute Change Orders 18
and 19 to Zovich Construction, Inc. for the New Juvenile Hall Project, Project No. 8811, Bid
Package 10590.

SUMMARY:
On March 28, 2017 passed Resolution 17-094 approving the award of the New Juvenile Hall Project, Project No. 8811, Bid Package 10590 (the "Contract") to the Zovich & Sons Inc., dba Zovich Construction. Resolution 17-094 further authorized the RMA Deputy Director of Public Works to execute individuals change orders of up to $150,000 so long as the total aggregate amount of individual change orders does not exceed $2,171,250. The total aggregate amount of all previously approved change orders in...

Click here for full text