File #: WRAG 18-099    Name: 3rd Quarter Financial Status Report
Type: WR General Agenda Status: Agenda Ready
File created: 5/3/2018 In control: Water Resources Agency Board of Directors
On agenda: 5/21/2018 Final action:
Title: Accept the Monterey County Water Resources Agency (MCWRA) Third Quarter Financial Status Report through March 31, 2018.
Attachments: 1. Board Report, 2. Fund 111 - Financial Summary Report, 3. Agency Financial Summary Report, 4. Board Order
Date Action ByActionResultAction DetailsSearchable Meeting DetailsVideo
No records to display.

Title

Accept the Monterey County Water Resources Agency (MCWRA) Third Quarter Financial Status Report through March 31, 2018.

Report

RECOMMENDATION:

It is recommended that the Monterey County Water Resources Agency Board of Directors:

 

Accept the Monterey County Water Resources Agency (MCWRA) Third Quarter Financial Status Report through March 31, 2018.

 

SUMMARY/DISCUSSION:

Year to date revenues for most of the Agency funds are at 48% of budget. The Agency receives most of its revenues from special assessments received in December and April. Hydro-electric revenue is at 97% of budget because of the January 2017 large winter storm and late 2018 Spring storms which results in more water to produce and maintain Nacimiento hydro-electricity output.  The Agency Expenditures are at 61% of budget as the Agency makes temporary repairs to the Nacimiento and San Antonio Dams because of the California Department of Water Resources - Division of Safety of Dams new requirements which were a result of the Oroville Dam failure during the winter of 2017.  The Agency anticipates recommendations by the end of Spring 2018 from the State Department of Water Resources for permanent fixes to the Dams as soon as the initial evaluations are reviewed by the California Department of Water Resources - Division of Safety of Dams.

 

The Agency continues to monitor expenditures as we approach the winter months. In addition, the Agency continues to work on refunding the Salinas Valley Water Project bond which will supplement funding for our aging infrastructure. 

 

On a consolidated basis the Agency financial performance is projected as follows:

 

FY 2017-18 Adopted Budget Beginning Fund Balance             $ 17,434,467

FY 2017-18 Projected Revenues                                                 $ 33,851,496

Total Estimate FY 2017-18 Available Funds                              $ 51,285,963

Less: 2017-18 Projected Expenditures                                        $ (36,537,950)

FY 2017-18 Projected Ending Fund Balance                              $ 14,748,013

 

OTHER AGENCY INVOLVEMENT:

None

 

FINANCING:

There is no financial impact in receiving this report.

 

 

Prepared by:                                           Cathy Paladini, Deputy General Manager, (831) 755-4860

 

Approved by:              _______________________________________________

                                    David E. Chardavoyne, General Manager (831) 755-4860

 

Attachments:

1.  Fund 111 -Financial Summary Report

2.  Agency Financial Summary Report

3.  Board Order