File #: 18-1068    Name: DA Modular Parking Lot
Type: General Agenda Item Status: Scheduled PM
File created: 10/16/2018 In control: Board of Supervisors
On agenda: 10/23/2018 Final action:
Title: a. Consider options for the former site of the County modular buildings 1, 2, 3, and 6 located behind the Superior Court at 240 Church Street (southwest corner of Gabilan and Church Streets); and b. Provide direction to staff regarding the preferred option for further and detailed staff investigation.
Sponsors: Public Works / RMA
Attachments: 1. Board Report, 2. Attachment A - Option 1 Concept, 3. Attachment B - Option 2 Concept, 4. Attachment C - Option 3 Concept, 5. Attachment D - Rough Order Comparison, 6. Attachment E - Location Map
Date Action ByActionResultAction DetailsSearchable Meeting DetailsVideo
No records to display.
Title
a. Consider options for the former site of the County modular buildings 1, 2, 3, and 6 located behind the Superior Court at 240 Church Street (southwest corner of Gabilan and Church Streets); and
b. Provide direction to staff regarding the preferred option for further and detailed staff investigation.
Report
RECOMMENDATION:
It is recommended the Board of Supervisors:

a. Consider options for the former site of the County modular buildings 1, 2, 3, and 6 located behind the Superior Court at 240 Church Street (southwest corner of Gabilan and Church Streets); and
b. Provide direction to staff regarding the preferred option for further and detailed staff investigation.

SUMMARY:
Modular buildings 1, 2, 3 and 6 were demolished and removed in September 2018 as part of the Monterey County Government Center East/West Wing Renovation Project. Board referral 2018.22 seeks to provide immediate direction to staff for short- and long-term plans for the property located behind the Superior Court at 240 Church Street (southwest corner of Gabilan and Church Streets). Questions have been presented on whether to create park and open space, expand parking, or something else. Staff has developed three options for the former site of the County modular buildings 1, 2, 3, and 6, including conceptual sketches and rough order of magnitude project estimates.

DISCUSSION:
Immediately following the removal of the modular buildings, woodchip mulch was placed throughout the open space as a temporary cover and the construction fencing removed. Mulch was selected as an inexpensive and low maintenance short-term measure, short of leaving it as dirt, while the Board of Supervisors weighs options for a long term permanent development of this site. Short term options for the Board to consider include:
- Option 1. Provide landscaped open space and buffer areas next to paved off-street parking in approximately equal parts (Attachment A).
- Option 2. Maximize off-street parking and ci...