File #: RES 19-181    Name: PLN170624 - Greer (Glass)
Type: BoS Resolution Status: Passed - RMA Land Use and Community Development
File created: 1/15/2019 In control: Board of Supervisors
On agenda: 1/29/2019 Final action: 1/29/2019
Title: PLN170624 - GREER (GLASS) Public hearing, continued from December 12, 2018, to consider: a. An appeal by Andres Czerwiak from the August 9, 2018 Zoning Administrator decision approving a Coastal Administrative Permit to allow the conversion of an existing test well to a permanent, single connection well and a Design Approval for related appurtenant components; and b. Approval of a revised project consisting of a Coastal Administrative Permit to allow the conversion of an existing test well to a permanent, two-connection well and a Design Approval for related appurtenant components, including a water pipe up to the property line[SWx1][SWx2]. Project Location: 124 Fern Canyon, Carmel Highlands[SWx3][SWx4], Carmel Area Land Use Plan Proposed CEQA Action: Categorical Exemption pursuant to Section 15303(e) of the CEQA Guidelines.
Attachments: 1. Board Report, 2. Attachment A - Project Data Sheet, 3. Attachment B - Draft Resolution, 4. Attachment C - Appeal request to BOS, 5. Attachment D - Letter, Fenton & Keller, 6. Attachment E - Letter, Noland, Hamerly, Etienne, Hoss, 7. Attachment F - ZA Resolution - 18-046, 8. Attachment G - Revised Water Agreement, 9. MS PowerPoint Presentation Presented at Hearing, 10. 39. Board Order, Resolution & Attachment
Title
PLN170624 - GREER (GLASS)
Public hearing, continued from December 12, 2018, to consider:
a. An appeal by Andres Czerwiak from the August 9, 2018 Zoning Administrator decision approving a Coastal Administrative Permit to allow the conversion of an existing test well to a permanent, single connection well and a Design Approval for related appurtenant components; and
b. Approval of a revised project consisting of a Coastal Administrative Permit to allow the conversion of an existing test well to a permanent, two-connection well and a Design Approval for related appurtenant components, including a water pipe up to the property line[SWx1][SWx2].
Project Location: 124 Fern Canyon, Carmel Highlands[SWx3][SWx4], Carmel Area Land Use Plan
Proposed CEQA Action: Categorical Exemption pursuant to Section 15303(e) of the CEQA Guidelines.
Report
RECOMMENDATION:
It is recommended that the Board of Supervisors adopt a resolution to:
a. Find that the appeal has been resolved by revision of the project;
b. Find that the project is categorically exempt pursuant to Section 15303(e) of the CEQA Guidelines; and
c. Approve a Coastal Administrative Permit, as revised, to allow the conversion of an existing test well to a permanent, two-connection well, in general conformance with the attached sketch and subject to the attached conditions of approval; and
d. Approve a Design Approval for appurtenant well facilities including: An electric powered pump, two (2) 119-gallon bladder tanks and water filtration system, water pipe up to the property line, two water meters to measure the quantity of water delivered to the respective properties, and a 5,000-gallon polyurethane water storage tank.

A draft resolution, including findings and evidence, is attached for consideration (Attachment B). Staff recommends approval subject to six (6) conditions.

PROJECT INFORMATION:
Project Owner: Timothy John Glass and Constance Glass
APN: 241-131-024-000
Agent: Nancy Isakson; Christine Kemp, E...