Title
PLN150889 - CALIFORNIA AMERICAN WATER CO (DESALINATION PLANT-- COMPONENT OF THE MONTEREY PENINSULA WATER SUPPLY PROJECT)
Public hearing to consider a Combined Development Permit for a 6.4 million gallon per day (mgd) desalination plant and related facilities covering an approximately 25-acre area as a component of the overall Monterey Peninsula Water Supply Project (MPWSP).
Project Location: 14175 Del Monte Blvd, Marina CA 93933, off of the private Charlie Benson Road, north of the City of Marina.
Proposed CEQA Action: Consider an Environmental Impact Report/Environmental Impact Statement (EIR/EIS) previously certified by the California Public Utilities Commission for the Monterey Peninsula Water Supply Project (SCH#2006101004).
Report
PROJECT INFORMATION:
Planning File Number: PLN150889
Owner: California American Water Company
APN: 229-011-021-000
Zoning: PG/40-D-S and F/40-D-S
Agent: Christopher Cook
Plan Area: Greater Monterey Peninsula Area Plan
Flagged and Staked: No
RECOMMENDATION:
It is recommended that the Planning Commission:
a. Consider the Environmental Impact Report/Environmental Impact Statement (EIR/EIS) for the Monterey Peninsula Water Supply Project, certified by the California Public Utilities Commission on September 13, 2018 (SCH#2006101004).
b. Approve a Combined Development Permit consisting of:
1. A Use Permit for a 6.4 million gallon per day (mgd) desalination plant and related facilities; and
2. An Administrative Permit and Design Approval to allow development in the Site Plan zoning district including the following facilities related to the desalination plant:
i. Pretreatment, reverse osmosis (RO), and post-treatment systems;
ii. Backwash supply and filtered water equalization tanks;
iii. Treated water storage and conveyance facilities;
iv. Brine storage and conveyance facilities;
v. Administration building and laboratory;
vi. Other related operational facilities; and
vii. 91,0000cy of grading (of 51,000cy of cut and 40,000cy...
Click here for full text