File #: PC 19-025    Name:
Type: Planning Item Status: Agenda Ready
File created: 4/16/2019 In control: Monterey County Planning Commission
On agenda: 4/24/2019 Final action:
Title: PLN150653 - CALIFORNIA AMERICAN WATER CO (CARMEL VALLEY PUMP STATION COMPONENT OF THE MONTEREY PENINSULA WATER SUPPLY PROJECT) Public hearing to consider the construction of a 764 square foot pump station to deliver water to the California American Water Company (CalAm) Monterey District service area as a component of the overall Monterey Peninsula Water Supply Project (MPWSP). Project Location: 26530 Rancho San Carlos Road, in Carmel Valley (Assessor's Parcel Number 015-251-030-000), Carmel Valley Master Plan area. [Mailing address is "Carmel."] Proposed CEQA Action: Consider an Environmental Impact Report/Environmental Impact Statement (EIR/EIS) previously certified by the California Public Utilities Commission for the Monterey Peninsula Water Supply Project (SCH#2006101004).
Attachments: 1. Staff Report, 2. Exhibit A - Project Data Sheet, 3. Exhibit B - Draft Resolution, 4. Exhibit C - Color Elevations, 5. Exhibit D - Carmel Valley LUAC Minutes, 6. Exhibit E - Vicinity map, 7. Exhibit F - Environmental Impact Report
Title
PLN150653 - CALIFORNIA AMERICAN WATER CO (CARMEL VALLEY PUMP STATION COMPONENT OF THE MONTEREY PENINSULA WATER SUPPLY PROJECT)
Public hearing to consider the construction of a 764 square foot pump station to deliver water to the California American Water Company (CalAm) Monterey District service area as a component of the overall Monterey Peninsula Water Supply Project (MPWSP).
Project Location: 26530 Rancho San Carlos Road, in Carmel Valley (Assessor's Parcel Number 015-251-030-000), Carmel Valley Master Plan area. [Mailing address is "Carmel."]
Proposed CEQA Action: Consider an Environmental Impact Report/Environmental Impact Statement (EIR/EIS) previously certified by the California Public Utilities Commission for the Monterey Peninsula Water Supply Project (SCH#2006101004).
Report
PROJECT INFORMATION:
Planning File Number: PLN150653
Owner: California American Water Co
APN: 015-251-030-000
Zoning: LDR/2.5-D-S-RAZ
Agent: John Chamberlain, AECOM
Plan Area: Carmel Valley Master Plan
Flagged and Staked: No

RECOMMENDATION:
It is recommended that the Planning Commission adopt a resolution to:
a. Consider the Environmental Impact Report/Environmental Impact Statement (EIR/EIS) for the Monterey Peninsula Water Supply Project, certified by the California Public Utilities Commission on September 13, 2018 (SCH#2006101004);
b. Approve a Use Permit and Design Approval for construction of a 764-square foot pump station, including grading of 36 cubic yards of cut and 720 cubic yards of fill, to deliver water to the California American Water Company (CalAm) Monterey District service area as a component of the overall Monterey Peninsula Water Supply Project (MPWSP); and
c. Adopt a Mitigation Monitoring and Reporting Plan

SUMMARY:
The project before the Commission is a Pump Station in Carmel Valley. It is a component part of the Monterey Peninsula Water Supply Project (MPWSP), which is a project by the California-American Water Company (CalAm) to develop a new wa...