File #: 20-731    Name: a. Accept as complete East Garrison Subdivision Phase 2 Infrastructure Improvements; b. Approve the release of the Security Bond for Faithful Performance and Laborers and Materialmen Bond No. 0190352 ($520,000 remainder) in accordance with Government
Type: General Agenda Item Status: Passed - RMA Administration
File created: 9/9/2020 In control: Board of Supervisors
On agenda: 9/29/2020 Final action: 9/29/2020
Title: a. Accept as complete East Garrison Subdivision Phase 2 Infrastructure Improvements; b. Approve the release of the Security Bond for Faithful Performance and Laborers and Materialmen Bond No. 0190352 ($520,000 remainder) in accordance with Government Code Section 66499.7 after the specified passage of time for recording claims or liens; and c. Accept Maintenance Bond No. 21BSBIJ9666, in the amount of $104,000, for the accepted sidewalk infrastructure improvements.
Attachments: 1. Board Report, 2. Attachment A- Location Map, 3. Attachment B-Security Bond for Faithful Performance, 4. Attachment C-Security for Laborers and Materialmen, 5. Attachment D-07-23-2020 Whitson Engineers Letter, 6. Attachment E-Maintenance Bond No. 21BSBIJ9666, 7. Item No. 34 Completed Board Order
Title
a. Accept as complete East Garrison Subdivision Phase 2 Infrastructure Improvements;
b. Approve the release of the Security Bond for Faithful Performance and Laborers and Materialmen Bond No. 0190352 ($520,000 remainder) in accordance with Government Code Section 66499.7 after the specified passage of time for recording claims or liens; and
c. Accept Maintenance Bond No. 21BSBIJ9666, in the amount of $104,000, for the accepted sidewalk infrastructure improvements.
Report
RECOMMENDATION:
It is recommended that the Board of Supervisors:
a. Accept as complete East Garrison Subdivision Phase 2 Infrastructure Improvements;
b. Approve the release of the Security Bond for Faithful Performance and Laborers and Materialmen Bond No. 0190352 ($520,000 remainder) in accordance with Government Code Section 66499.7 after the specified passage of time for recording claims or liens; and
c. Accept Maintenance Bond No. 21BSBIJ9666, in the amount of $104,000, for the accepted sidewalk infrastructure improvements.

SUMMARY/DISCUSSION:
The recommended action will allow the County to accept as complete the East Garrison Phase 2 Project (Project) infrastructure improvements and approve the release of the remaining balance of two bonds associated with construction and the acceptance of a Maintenance Security Bond for the accepted sidewalk infrastructure improvements. Attachment A provides a location map for the Project.

On March 1, 2016, the Monterey County Board of Supervisors accepted a completed portion of the Project's Infrastructure Improvements, including road, drainage, and infrastructure improvements with the exception of the concrete sidewalks fronting the residential lots, which would be constructed when the houses on those lots were completed. The bonds (Attachments B and C) were reduced from $5,569,000 to $520,000.

The Subdivider's Engineer provided a letter advising of the completion of the Project's infrastructure improvements according to the approved p...