Title
It is recommended the Board of Supervisors:
Authorize the Chief Executive Officer for Natividad Medical Center (NMC) or his designee to execute amendment No. 5 to the agreement (A-12753) with RBB Architects Inc. for architectural services for the Radiology Modernization Project at NMC pursuant to the Request for Qualifications (RFQ) # 9600-54, extending the agreement an additional three (3) month period (March 1, 2021 through May, 31, 2021) for a revised full agreement term of September 23, 2014 through May 31, 2021.
Report
RECOMMENDATION:
It is recommended the Board of Supervisors:
Authorize the Chief Executive Officer for Natividad Medical Center (NMC) or his designee to execute amendment No. 5 to the agreement (A-12753) with RBB Architects Inc. for architectural services for the Radiology Modernization Project at NMC pursuant to the Request for Qualifications (RFQ) # 9600-54, extending the agreement an additional three (3) month period (March 1, 2021 through May, 31, 2021) for a revised full agreement term of September 23, 2014 through May 31, 2021.
SUMMARY/DISCUSSION:
NMC is in the construction stage of modernizing the Radiology Department on the first floor of Building 500. The Radiology Department is adding two new Computerized Tomography (CT) scanners, a new Magnetic Resonance Imaging (MRI) as well as creating an Angiography hybrid suite for Interventional Radiology (IR).
The construction was originally forecasted to occur over a 24-month period with construction occurring into 4 phases to maintain services during the remodel. The construction was originally forecasted to occur over a 24-month period, with construction occurring into 4 phases to maintain services during the remodel. Construction started on September 4, 2018, and has currently completed 90% of the project. The Coronavirus (COVID-19) pandemic is continually generating unprecedented delays and disruptions to the Radiology Modernization project by effecting equipment manufacturin...