File #: A 21-079    Name: RBB Architects Amendment 5
Type: BoS Agreement Status: Passed - Natividad Medical Center
File created: 3/8/2021 In control: Board of Supervisors
On agenda: 4/20/2021 Final action: 4/20/2021
Title: It is recommended the Board of Supervisors: Authorize the Chief Executive Officer for Natividad Medical Center (NMC) or his designee to execute amendment No. 5 to the agreement (A-12753) with RBB Architects Inc. for architectural services for the Radiology Modernization Project at NMC pursuant to the Request for Qualifications (RFQ) # 9600-54, extending the agreement an additional three (3) month period (March 1, 2021 through May, 31, 2021) for a revised full agreement term of September 23, 2014 through May 31, 2021.
Attachments: 1. Board Report, 2. RBB Architects Inc. Renewal and Amendment No. 5, 3. RBB Architects Amendment 4.pdf, 4. RBB Architects Amendment 3.pdf, 5. RBB Architects Amendment 2.pdf, 6. RBB Architects Amendment 1.pdf, 7. RBB Architects Agreement.pdf, 8. Completed Board Order Item No. 34
Related files: A 21-427
Title
It is recommended the Board of Supervisors:
Authorize the Chief Executive Officer for Natividad Medical Center (NMC) or his designee to execute amendment No. 5 to the agreement (A-12753) with RBB Architects Inc. for architectural services for the Radiology Modernization Project at NMC pursuant to the Request for Qualifications (RFQ) # 9600-54, extending the agreement an additional three (3) month period (March 1, 2021 through May, 31, 2021) for a revised full agreement term of September 23, 2014 through May 31, 2021.

Report
RECOMMENDATION:

It is recommended the Board of Supervisors:

Authorize the Chief Executive Officer for Natividad Medical Center (NMC) or his designee to execute amendment No. 5 to the agreement (A-12753) with RBB Architects Inc. for architectural services for the Radiology Modernization Project at NMC pursuant to the Request for Qualifications (RFQ) # 9600-54, extending the agreement an additional three (3) month period (March 1, 2021 through May, 31, 2021) for a revised full agreement term of September 23, 2014 through May 31, 2021.

SUMMARY/DISCUSSION:

NMC is in the construction stage of modernizing the Radiology Department on the first floor of Building 500. The Radiology Department is adding two new Computerized Tomography (CT) scanners, a new Magnetic Resonance Imaging (MRI) as well as creating an Angiography hybrid suite for Interventional Radiology (IR).

The construction was originally forecasted to occur over a 24-month period with construction occurring into 4 phases to maintain services during the remodel. The construction was originally forecasted to occur over a 24-month period, with construction occurring into 4 phases to maintain services during the remodel. Construction started on September 4, 2018, and has currently completed 90% of the project. The Coronavirus (COVID-19) pandemic is continually generating unprecedented delays and disruptions to the Radiology Modernization project by effecting equipment manufacturin...

Click here for full text