File #: WRAG 21-078    Name: Reservoir Release Schedule - BOD
Type: WR General Agenda Status: Agenda Ready
File created: 4/16/2021 In control: Water Resources Agency Board of Directors
On agenda: 4/26/2021 Final action:
Title: Consider adopting a Release Schedule for the Nacimiento and San Antonio Reservoirs for 2021.
Attachments: 1. Board Report, 2. Draft Release Schedule 2021, 3. Board Order
Title
Consider adopting a Release Schedule for the Nacimiento and San Antonio Reservoirs for 2021.
Report
RECOMMENDATION:
It is recommended that the Monterey County Water Resources Agency Board of Directors:

Adopt a Release Schedule for the Nacimiento and San Antonio Reservoirs for 2021

SUMMARY/DISCUSSION:
he Agency began operating the Salinas River Diversion Facility (SRDF) in 2010, delivering river flows for diversion during the facility's first four seasons (2010-2013). Extended drought conditions then resulted in insufficient reservoir levels for operation during the next three years (2014-2016). The Winter of 2016-2017 brought large inflow volumes into the reservoirs enabling resumption of conservation releases and SRDF operation during both 2017 and 2018, despite limited inflow during the 2017-2018 winter. A wet 2018-2019 winter provided significant Nacimiento Reservoir inflow and storage for a complete 2019 SRDF operation season; combined reservoir inflow during the 2018-2019 and 2019-2020 winters provided sufficient reservoir storage for continued conservation releases in 2020. The winter of 2020-2021 produced only one significant inflow event, resulting in combined reservoir storage volumes currently sufficient for only an abbreviated SRDF operation season, as detailed in the proposed 2021 release schedule (attached).

The proposed 2021 release schedule assumes no additional reservoir inflow than the totals seen to date. As seen in the schedule, current reservoir storage provides adequate releases to establish and maintain conservation flows to recharge the groundwater basin, operate the SRDF from April to July of 2021, and meet the operational requirements of both the currently withdrawn Salinas Valley Water Project National Marine Fisheries Service Biological Opinion and the State Water Board appropriative water rights held by the Agency for the Nacimiento and San Antonio rivers.

This release schedule will be updated monthly based on actual wea...

Click here for full text