File #: BC 22-116    Name: Parjaro Levee Loan
Type: Budget Committee Status: Agenda Ready
File created: 8/16/2022 In control: Budget Committee
On agenda: 8/31/2022 Final action:
Title: Support a request by Monterey County Water Resources Agency that the Monterey County Board of Supervisors approve and authorize forgiveness of the loan of $950,000 issued to Monterey County Water Resources Agency, financed by the County's General Fund Cannabis Tax Assignment for the Pajaro River Flood Risk Management Project Design Phase.
Attachments: 1. BC Report, 2. 21-405 BOS Resolution, 3. Muscle Wall Cost Analysis

Title

Support a request by Monterey County Water Resources Agency that the Monterey County Board of Supervisors approve and authorize forgiveness of the loan of $950,000 issued to Monterey County Water Resources Agency, financed by the County’s General Fund Cannabis Tax Assignment for the Pajaro River Flood Risk Management Project Design Phase.

Report

RECOMMENDATION:

It is recommended that the Budget Committee:

 

Support a request by Monterey County Water Resources Agency that the Monterey County Board of Supervisors approve and authorize forgiveness of the loan of $950,000 issued to Monterey County Water Resources Agency, financed by the County’s General Fund Cannabis Tax Assignment for the Pajaro River Flood Risk Management Project Design Phase.

 

SUMMARY/DISCUSSION:

The Pajaro River Federal Flood Control Project was built in 1949 by the United States Army Corps of Engineers (“USACE”) and is maintained jointly by the Santa Cruz County Flood Control and Water Conservation District - Zone 7 (“Zone 7”) and the Monterey County Water Resources Agency (“MCWRA”).

 

USACE and the non-federal sponsors (Zone 7 and MCWRA) entered into a Design Agreement (“DA”) in May 2021.  The DA estimates a total project cost of $7,100,000, cost shares are projected to be $4,615,000 for the federal government, $1,342,500 for Zone 7 and $1,142,500 for MCWRA over three years.  Non-federal cost share contributions made by Zone 7 and MCWRA would be eligible for reimbursements by the California State Department of Water Resources (DWR) thru the Coast Watershed Funding Agreement and a Subventions Agreement.

 

On November 16, 2021, Monterey County Board of Supervisors authorized a loan up to $950,000 over two years to MCWRA to pay its non-federal cost share of the project with the condition that it will be repaid with reimbursements from DWR. MCWRA borrowed $658,500 in Fiscal Year 2021-22 and submitted a reimbursement request to DWR in July 2022.  A request of the second installment in FY 2022-23 for $291,500 was submitted to the County by MCWRA on July 7, 2022.

 

The Pajaro Regional Flood Management Agency (“PRFMA”) was formed under the Joint Exercise of Powers Act, Government Code section 6500 et seq., pursuant to a Joint Exercise of Powers Agreement (“JPA Agreement”) dated July 21, 2021, in order to coordinate, finance, acquire, construct, improve, operate or maintain flood management infrastructure on the Pajaro River in Santa Cruz and Monterey Counties.  Its Member Agencies are County of Santa Cruz, Zone 7, County of Monterey, City of Watsonville and MCWRA. The PRFMA is the lead local agency to work with USACE in continuing the Pajaro River Federal Flood Control Project, which is currently maintained jointly by Zone 7 and MCWRA. 

 

A recent survey of the Pajaro Levee indicates that a portion of the levee crest on the Monterey County side requires restoration, which is estimated to cost approximately $3.5 to $4.0 million assuming construction in 2026.  The area that needs crest restoration is upstream of USACE’s Pajaro River Federal Flood Control Project and modeling identifies this as an area of concern.  A temporary protective measure within the restoration reach is to install a temporary Muscle Wall of 10,510 feet length for the high priority areas. MCWRA, working with PRFMA has secured 1,000 feet of Muscle Wall from DWR. The total estimate of the complete Muscle Wall is $859,227.53 for materials and there will be additional cost for storage and labor.  Materials will be paid by MCWRA and there may also be additional work costs that will be performed by PRFMA.

 

PRFMA and MCWRA staff understand this area to pose a potential public safety risk and believe this temporary protective measure will reduce flood risk.

 

The amount estimated for the Muscle Wall exceeds MCWRA’s Fund 112 (Pajaro Levee) fund balance.  The primary funding source of Fund 112 is flood benefit assessments of Zone1/1A, which pays for routine operations and maintenance activities and is not sufficient to cover unexpected cost such as installation of the Muscle Wall. MCWRA cannot borrow from most other MCWRA funds due to restrictions specific to the MCWRA Zones. The funds that could be utilized do not have sufficient fund balance to pay the remaining amount.  Reimbursements from DWR, which was originally intended to repay the County loan is the only possible revenue MCWRA has been able to identify for this purpose.

 

OTHER AGENCY INVOLVEMNT:

MCWRA is working with the PRFMA, Office of the County Counsel, CAO’s office and County Budget Office on the topic. 

 

FINANCING:

The FY 2022-23 estimated starting balance of the Cannabis Tax Assignment (including the use of the assignment as a funding source) is $2,070,115.50.  The balance reflects $977,007 set aside for the Jail House Addition Change Order No. 440 and the second loan installment of $291,500 for WRA for the Pajaro Levee Project.

 

The County’s FY 2022-23Adopted Budget does not include a re-payment from MCWRA for the loan. The MCWRA Fiscal Year 2022-23 Adopted Budget for Fund 112 includes the planned repayment for $658,500 to the County.  Therefore, approval of the loan forgiveness will not have an impact to the County’s Adopted Budget. The only impact is a lower Cannabis Tax Assignment balance since the loan would be forgiven.

 

DWR will reimburse MCWRA’s non-federal share contributions under the Coast Watershed Funding Agreement that PRFMA has executed with DWR.  The first invoice for $658,500 is scheduled for submission in July 2022 and the second invoice for $291,500 will be submitted in October 2022.   The reimbursements from DWR under the Coast Watershed Funding Agreement are expected within 90 to 120 days after DWR receives the invoices.

 

 

Prepared by:          Nan Kyung Kim, Finance Manager III, (831) 755-4861

                              Monterey County Water Resources Agency    

                     

 

Approved by:       ______________________________________

                             Brent Buche, General Manager, (831) 755-4860

                             Monterey County Water Resources Agency

 

 

Attachment:

1.                     Resolution 21-405

2.                     Muscle Wall Cost Analysis