Title
a. Adopt the Monterey County 2018 Construction Task Catalogs, Job Order Contracting (JOC) 2018 - Roads & Bridges Project Specifications and JOC 2018 - Facilities Project Specifications, and Monterey County 2018 Technical Specifications for JOC 2018, Project No. JOC 2018, Bid No. Roads & Bridges 2018-01, Bid No. Roads & Bridges 2018-02, and Bid No. Roads & Bridges 2018-03, and Project No. JOC 2018, Bid No. Facilities 2018-01, Bid No. Facilities 2018-02, and Bid No. Facilities 2018-03;
b. Authorize the Resource Management Agency Director to advertise for bids in the Monterey County Weekly.
Report
RECOMMENDATION:
It is recommended that the Board of Supervisors:
a. Adopt the Monterey County 2018 Construction Task Catalogs, Job Order Contracting (JOC) 2018 - Roads & Bridges Project Specifications and JOC 2018 - Facilities Project Specifications, and Monterey County 2018 Technical Specifications for JOC 2018, Project No. JOC 2018, Bid No. Roads & Bridges 2018-01, Bid No. Roads & Bridges 2018-02, and Bid No. Roads & Bridges 2018-03, and Project No. JOC 2018, Bid No. Facilities 2018-01, Bid No. Facilities 2018-02, and Bid No. Facilities 2018-03;
b. Authorize the Resource Management Agency Director to advertise for bids in the Monterey County Weekly.
SUMMARY:
Recommended actions include the adoption of the 2018 Monterey County Job Order Contracting (JOC) Task Catalogs for the JOC 2018 contracts (2018 JOC Program), and advertising for bids (2018 JOC Program). In light of the many capital projects slated for Fiscal Years (FYs) 2018-19 and 2019-20, it is recommended that three (3) Roads & Bridges and three (3) Facilities Job Order Contracts be issued each for $4,904,581 with $25,000 worth of work guaranteed in each contract.
DISCUSSION:
California Public Contract Code Section 20128.5 provides that counties may award annual contracts for repair, remodeling, or other repetitive work to be done according to unit prices, commonly referred to as Job Order Contracting (JOC).
In April 2013, the Board of Supervisors (Board) approved an Agreement between the County of Monterey (County) and The Gordian Group, Inc. to provide the County with a JOC System. The Gordian Group job order contracting system uses an extensive catalog of construction tasks and associated technical specifications containing over 260,000 individual items specifically designed for Monterey County. Per California Public Contract Code (PCC) Section 20128.5, the Board may award individual annual contracts which shall not exceed the statutory maximum contract value. Per PCC Section 20128.5, each awarded contract has a maximum contract value (MxCV) that is adjusted annually to reflect the percentage change in the California Consumer Price Index (CPI), for repair, remodeling, or other repetitive work to be done according to unit prices. The percentage change in the CPI is calculated and provided by the Department of Industrial Relations (DIR). Per DIR’s annual determination, the MxCV for JOC contracts was increased from $4,766,357 in 2017 to $4,904,581 in 2018. County JOC specifications provide for a one (1) year term with $25,000 worth of work guaranteed for each individual contract.
County JOC specifications require Contractors to provide a letter from a bonding company stating their ability to obtain Payment and Performance Bonds for the MxCV. This year, for Facilities Bids, Staff recommends that Monterey County require the successful bidder to furnish an initial payment bond and a performance bond for approximately fifty percent (50%) of the MxCV, each in the amount of $2,500,000. If the aggregate Job Orders issued under any of the awarded Facilities Contracts exceed $2,500,000, an increase in the Payment and Performance bonds for the corresponding Facilities Contract will be required in an amount not less than one hundred percent (100%) of the MxCV of $4,904,581. The lower initial bonding requirement for Facilities Contracts is recommended to attract Contractors who may otherwise not bid on the Facilities projects due to the high bonding requirement relative to the guaranteed work of $25,000. The initial bonding requirement for Roads and Bridges Contracts remains set at one hundred percent (100%) of the MxCV because it is anticipated that Roads and Bridges Contractors may reach the MxCV cap earlier than Facilities Contractors. For Roads and Bridges Bids, successful bidders shall furnish payment bonds and performance bonds, each in the amount of the MxCV of $4,904,581 which bonds shall remain in force for the duration of the annual contract term and until completion of all outstanding Job Order(s).
Since its inception in 2013, the JOC program has proven of value to RMA-Public Works, Parks and Facilities by improving economy and efficiency in completing a number of public works projects, including urgent and time sensitive projects. Since 2013, the County has issued 343 Job Order Contract projects totaling $49,033,206 (including 181 Roads and Bridges projects totaling $22,945,555 and 162 facilities projects totaling $26,087,652). The JOC Program has enabled the County to implement a higher volume of maintenance, repair and remodeling projects which would otherwise not be possible due to limited project management staff time.
Following the selection of successful bidders, RMA-Public Works, Parks and Facilities recommends awarding three (3) separate Roads and Bridges Contracts and three (3) separate Facilities Contracts to allow RMA-Public Works, Parks and Facilities the option to use alternate contractors in the event that any of the selected contractors is/are deemed nonresponsive or has/have poor performance. Any Job Order that would exceed $1 Million will be brought to the Capital Improvement Committee (CIC) and Budget Committee (BC) prior to issuing the Notice to Proceed. The contracts will apply to eligible projects during FYs 2018-19 and 2019-20. The individual annual JOC contracts will be issued for a 12-month contract period. Any capital and/or facilities maintenance repair project that falls into the following fiscal year will be budgeted. RMA-Public Works, Parks and Facilities will continue to provide quarterly JOC status reports to the CIC which would include scope, cost, schedule, source of previously appropriated/expended funds, and contractor evaluations.
A “Notice to Bidders” will be duly advertised in a newspaper of general circulation per California Public Contract Code Section 20150.8. JOC 2018 contracts are anticipated to be awarded in October 2018. Specific eligible projects have not yet been identified.
The County’s JOC procurement process requires the RMA to first seek Board approval to adopt plans and specifications and advertise for bids followed by a second request for Board approval to award selected contractors. California Public Contract Code Section 20128.5 requires Board approval to award contracts to selected contractors.
OTHER AGENCY INVOLVEMENT:
The Office of the County Counsel- Risk Management and Auditor-Controller, have reviewed and approved the Project Specifications as to form and legality, fiscal terms, and insurance provisions, respectively.
FINANCING:
The 2018 JOC Program would provide for six (6) individual Job Order Contracts with a cap of $4,904,581 for a total of $29,427,486 - three (3) for Roads & Bridges and three (3) for Facilities. Expenditures will be within and not exceed the FY 2018-19 or FY 2019-20 Adopted Budgets. Funding for JOC projects, including applicable Gordian Group fees, is contained within the adopted FY 2018-19 budget allocations for various funds; Fund 401 - Facilities Maintenance Projects, Fund 402 - Capital Projects, Fund 404 - Facilities Master Plan Projects, Fund 002 - Road Fund, the respective County Service Area or County Sanitation District Fund, and the individual department authorizing the project. A five percent (5%) License Fee to utilize the JOC program is payable to the Gordian Group only if and when a Job Order is issued to a JOC Contractor. Optionally, as needed, the County may utilize JOC Project Management services for an additional 5.95% fee. Gordian fees are contained in the overall eligible project budgets.
To date, the County has issued 343 Job Order Contract Projects totaling $49,033,206. Gordian License Fee and project management fees totaled $3,038,887 or an overall average of six percent (6%) of the total construction contract value to date. This fee is lower than the industry standard of ten percent (10%) for Construction Management fees.
BOARD OF SUPERVISORS STRATEGIC INITIATIVES:
The JOC program helps with providing efficient and effective government operations by allowing improved processing for smaller and more urgent projects. Monterey County has multiple documents to help identify and address critical infrastructure needs (Pavement Management Plan, Americans with Disabilities Act (ADA) Transition Plan, Facility Asset Report, Municipal Climate Action Plan, etc.). Taking these documents into account, a Five-Year Capital Improvement Program is adopted each year to efficiently allocate resources for projects with budgets over $100,000 to help sustain the infrastructure. The JOC program projects include improvements to health and safety facilities. Provision of adequate County facilities and infrastructure improves the quality of life for County residents and supports economic development results.
Related Board of Supervisors Strategic Initiatives include:
X Economic Development
X Administration
X Health & Human Services
X Infrastructure
X Public Safety
Prepared by: Florence Kabwasa-Green, PM II, (831) 755-4805
Approved by: Neville Pereira, P.E., CBO, Interim RMA Deputy Director of Public Works, Parks and Facilities
Approved by: Carl P. Holm, AICP, RMA Director
The following attachments are on file with the Clerk of the Board:
Attachment A.1 - Monterey County 2018 JOC Roads and Bridges Construction Task Catalog
Attachment A.2 - Monterey County 2018 Facilities Construction Task Catalog
Attachment B - JOC 2018 Roads & Bridges Project Specifications
Attachment C - JOC 2018 Facilities Project Specifications
Attachment D.1 - Monterey County 2018 JOC Roads and Bridges Technical Specifications
Attachment D.2 - Monterey County 2018 Facilities Technical Specifications
Exhibit 1: JOC System License and Fee Agreement
Exhibit 2: Contractor Evaluation
Exhibit 3: CDBG Standard Provisions & Requirements
Exhibit 4: Federal Provisions-Caltrans Local Assistance Manual
Exhibit 5: FEMA Standard Provisions and Requirements
Exhibit 6: Monterey County Cabling Specifications
Exhibit 7: Notice to Bidders