File #: 15-1164    Name: Quarterly Capital Improvement Project 9-30-15
Type: General Agenda Item Status: Agenda Ready
File created: 10/19/2015 In control: Capital Improvement Committee
On agenda: 11/9/2015 Final action:
Title: Receive a quarterly report on Resource Management Agency-Public Works Capital Improvement Projects for the period ending September 30, 2015.
Sponsors: Public Works / RMA
Attachments: 1. FY15-16 Capital Improvement Projects Report July 1-September 30 2015 BC
Title
Receive a quarterly report on Resource Management Agency-Public Works Capital Improvement Projects for the period ending September 30, 2015.

Report
RECOMMENDATION:
It is recommended the Capital Improvement Committee receive a quarterly report on Resource Management Agency-Public Works Capital Improvement Projects for the period ending September 30, 2015.

SUMMARY/DISCUSSION:
The Resource Management Agency - Public Works (RMA - PW) staff administers capital projects for Monterey County. The attached FY 2015-16 Capital Improvement Projects Status Report provides a summary for 36 capital projects totaling over $329 million: 21 Road and Bridge ($139.5 million), and 15 other ($190.4 million) and includes project costs, development phase, and status. During this quarter, 4 projects were completed. Of the remaining 32 projects in progress: 9 are under construction and 23 are in the Design/Environmental Phase. The following project narrative provides updates on completed projects and projects with significant activity during the reporting period of July 1 - September 30, 2015.

COMPLETED PROJECTS

River Road Overlay and River Road Delineation Projects
The project consisted of rehabilitating River Road with pavement recycling methods; from Parker Road to Chualar River Road, approximately 3.9 miles. The project is 100% funded by monies from the Transient Occupancy Tax. The project was constructed concurrently with the River Road Pavement Delineation project. All construction work for both projects has been completed and project closeout is underway.

Arroyo Seco Road - Project CA PFH 12-1(2)
The project consisted of rehabilitating Arroyo Seco Road with hot-mix-asphalt; from Los Padres National Forest park entrance to Carmel Valley Road, approximately 4.4 miles. Federal Highway Administration (FHWA) is the lead on the project. Monterey County provided oversight. All construction work has been completed and project closeout is underway.

Davi...

Click here for full text